P6 Pro v8.3.2 Baseline Update Function errors related to dates
I'm trying to run a baseline update. I did the same thing successfully back in May. At that time, I had some errors about resource start and finish not matching activity start and finish. I cranked out a report, found a handful of mismatches (I still am baffled by why the system makes some resource dates not match the activity dates and then gives me hell because they are different). and ran it and it seemed to work fine.
Anyway, this time I ran into the same thing. Fixed a couple of places I found this same mismatch (not as many as the number of SEVERE Errors that were thrown), then ran it again and got like 40+ errors that look like this: