I have just taken over a project and cannot get the correct values to come out relating to resource usage.  On an activity view the values on the activities summarise up to the total value but when I run a report the values are far too low.

When I review the resource from the assignments tab.  The activity values seem to match but the summaries do not reach the total of the activities.  From below you can see that the 5 activities should total more that 3.7.  What wrong?