Which is the best way to import both WBS & Activities in P6 EPPM ?
Hi All,
I was trying to translate a WBS in Excel to a Template in P6 EPPM Projects. The option I currently use is 'Import from Excel' to import only activities from my excel, later structure them in Activities tab by adding WBS hierarchy & then moving activities to respective WBS nodes. I know there will be an easier way to do this which I'm unaware of. Could you please guide or suggest me on this procedure?
Thanks in advance!
Note: I'm currently on EPPM 16.2. But this is the procedure I have been using since EPPM 8.3
Regards,
Prashanthi