Hi,

We are facing strange scenario where we ahve batch of 2700  KG for which we issue material in month of august for 2700 KG

then we completed first lot with 900 KG on 17 aug 2016 and remaining 1800 on 23 Aug 2017 when checked accounting it is giving

zero accounting for 23 Aug 2016 dut to which COGS affected badly

Earlier we have used profile option as gmf:Virual back flush entries but due to this entire yield will be loaded on item cost means if WIP

issue is for .1 and completion is 200 KG then systm calcualtes item cost based on 200 KG for that item cost istead for .1 KG due to this there is huge difference generated in item cost

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center