Does PM Forecast function removes the suppress activities?
Hi,
We are having one PM - one actvity setup ( Date based) and suppresses 3M PM jobs of an asset with 1 Month PM jobs & 1m PM with 1 week PM .But when we look at the forecast for this asset suppress activities are showing. Is this a standard functionality or a bug?
Tolence on PM setup is blank
Also, does it look for PM rule criteria for suppressing, we have few PM jobs with Schedule start date and few with Actual end date as the scheduling options criteria
Regards
Prakash