Wrong Planned Value Cost

edited Nov 3, 2016 5:15AM in Primavera (MOSC) 4 commentsAnswered

Hi all,

I'm facing on a problem on P6 PPM (P6 Professional) about Planned Value Cost for EV analysis.

When I have a manual curve on a resource in an activity, and I use for Earned Value calculation the option When calculating Earned Value from a baseline use At Completion value with current dates, the planned value cost seams to be the planned value units with the currency symbol!!!

Let me better explain the situation:

I created a Test project (Planned Start on 1° November, Planned Finish on 30th December). I have only 1 task (Start the 1° November and Finish the 30th December). I assigned to that activity one resource that has as price/unit 10€/h. So I put as Budget unit on November, 100h and on December 50h, as you can see:

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center