How to default chargeable flag: for Transaction Control at Project and task level...???
a. Go to Projects responsibility
b. Navigate to Projects
c. In the FIND PROJECT , query the project
d. Click Open in the Project Summary form
e. In the Projects Templates form, Under Options, Put the cursor on option name = TRANSACTION CONTROLS and click on DETAIL button.
f. In the Transaction Controls form, check the Chargeable checkbox
g. Save
h. Close the Transaction Controls form
i. In the Projects Templates form, under Options, Put the cursor on option name = TASKS and click on DETAIL button.
j. For each TASK , click on OPTIONS button.
k. In the Task Options form, double click on the option name = TRANSACTION CONTROLS.