Can a Static Activity Bar Display Incremental Progress as % of Duration?
A recent scheduling specification is asking for schedule progress to displayed in 10% increments on the activity bar. I know this is not how P6 NORMALLY displays actual progress. I'm thinking the client is referring to an Excel-type function where a bar does not change from the planned dates and displays the progress incrementally. As far as I know, there is no capability for this type of display in P6.