Lead Time Lot Size...does it work for Buy items?
Say a buy item has this setup at the org level:
Preprocessing = 1 day
Processing = 10 days
PostProcessing = 2 days
If a Lead Time Lot Size is set to 10...does that imply the processing time is 10 days and if a planner ordered say 30 the processing time would be tripled?