Pushing the Demand in EDD plan
Hi,
We have a business requirement where in Demand needs to be nullified for a particular week and pushed to next week and so on .
Ours is a Constrained EDD plan. Is there any way to achieve this.
The scenario will be as below:
BEFORE (qty) 1500 2000 2500 3000
AFTER (qty) 1500 0 2000 2500 & so on...
Thanks,
ASP.