roll up issue in loadHier
I encountered a prod hierarchy roll-up issue. Even though I removed all entries with following highlighted key words, loadHier still was failed.
Questions:
1) Any body met the same issue before or knows how to trouble shoot?
dbbackupmanager completed successfully
Begin multiparent check for PRODMASTER array.
Begin multiparent check for NEW_DIM_SKPC array. (Add old ext map.)
Error roll-up conflict base position LC_000000001134922003 defined
SKDC:000000001134922003 --> STY:PO3048S95/3158_DL10FALF_100510390_9999
Whereas base position PV_000000001134922003 defined
SKDC:000000001134922003 --> STY:PO3048S95/3158/19_DL10FALF_100510390_9999
Error roll-up conflict base position SG_000000001134922003 defined
SKDC:000000001134922003 --> STY:PO3048S95/3158_DL10FALF_100510390_9999
Whereas base position