Procurement - EBS (MOSC)

MOSC Banner

Why PR lines automatically cancelled after cancelled PO shipment?

edited Jan 12, 2017 5:35PM in Procurement - EBS (MOSC) 3 commentsAnswered

Hi,

I found some PR lines was automatically cancelled by the system. As I checked, those PR lines was fully delivered.

I want to know:

1. Why the system mark cancelled flag in PR lines? Because PR summary displayed quantity delivered align with the receiving transaction.

2. The system can be setting up to prevent automatically canceled PR lines after PO shipment was cancelled?

I require this information for discussion with our team. Thank you in advance.

Regards,

Pathikorn