The main planning attribute of item 5060403110053 is as below:

ITEMORGSSafety Stock Planning MethodDemand PeriodDays of CoverFixed Days SupplyForecast TypePostprocessing DaysProcessing Daysforecast bucket type
5060403110053FTZ4Days of Cover302015Sales Type45753

The item has monthly sales forecast as its only demand, the bucket type of demand is 3. That means period type.

The forecast for this item is as below,

USING_REQUIREMENT_QUANTITYUSING_ASSEMBLY_DEMAND_DATE
81182017/1/2
77032017/2/1
68252017/3/1
98512017/4/3
10292017/5/1
48152017/6/1
86932017/7/3
91692017/8/1

The parameter in  supply: advanced options of the plan is:

Horizon for Average Daily Demand: 30

Safety Stock Planning Method: Use safety stock quantities

Apply safety stock change interval to all items:checked

Tagged:

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center