Hi, 

We are using ASCP 12.2.5 with discrete mfg. We have a requirement with our customer. The item1 is manufactured in  Org ABC and transferred to Org XYZ. The demand for the item item1 is set at Org XYZ. But we have a restriction that the org XYZ cannot produce more than 100,000 quantities a week. So if we have demand for more than 150,000 for that week,  two planned orders(in Org ABC) should be suggested 1 planned order for 100,000 qty for that week and another planned order for the next week for 50,000.  Please advise. 