Hi Team,

We are using PMAC costing and are on 12.2.4. I am trying to map the OSP Resource cost to PO Price. Hence in Plant Resource form, i have setup "Cost Source = PO Price". Please note that we do not have resource cost defined in Oracle.

When i run the ACP (Actual Cost Process), it gives an warning 'Cannot find the nominal cost for org code'. And due to this OSP charges are not getting rolled-up to Product cost.

Then for testing purpose, i have defined the resource cost as $1. And run the ACP again, this time proper costing happened and OSP charges are got rolled-up to product cost.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center