Claim Digger Planned Start Dates
Claim Digger is reporting future Planned Start dates for activities already actualized. Total Float is also being reported in hours rather than days. Are these issues with P6 configuration or am I missing a critical step? I am using P6 Professional R15.2
CLAIM DIGGER REPORT | SCHEDULE | |||||
Activity Id | Activity Name | New Planned Start Date | Old Planned Start Date | Days Lost | Actual Start | |
SC03470 | Model 11 Annex (002) - Submit As Built Drawings | 9/13/2017 | 10/10/2016 | 338 | ||
D02735 | Model 1 Arts Center Station (004) - Survey Test | 5/2/2017 | 9/25/2015 | 585 | Aug-07-12A | |
D02730 | Model 1 Arts Center Station (004) - Design Narrative | 5/2/2017 | 9/25/2015 | 585 | Aug-08-12A | |
D02720 | Model 1 Arts Center Station (004) - Survey | 5/2/2017 | 9/25/2015 | 585 | Aug-07-12A |