Hi,

We are looking at beginning to use rework BOMs, type "RWK".

When you have two BOMs loaded, is there a way for the system to force MRP to use one type of BOM (for planning procurement and generating work orders) and the costing to use another ?

We would want the cost roll up to use the M type BOM, and MRP and work order generation to automatically use the RWK type BOM. Is there a setting to allocate this at an item level ?

Regards,

Jayesh Patel.