ASCP 24-Hour Resource Capacity
We are newly implementing ASCP (Release 12.2.4) and I am having an issue where a handful of resources collected from our source system (JDE E1) are being reflected in the Resource Availability as 24-hours. The box at the top right is selected as 24 Hour Resource and I am unable to unselect it.
When reviewing the setup of this resource in JDE E1, we have 2 11-hour shifts setup so not only would I expect to see both of those shifts, but I would also expect to see 22 hours available with the 24 Hour Resource box unchecked.
When reading through our VCP - ODS mapping document, it appears the source table (MSC_DEPARTMENT_RESOURCES) which stores the resources available for planning is populating a value of 1 in the AVAILABLE_24_HOURS_FLAG field of this table. This value of 1 is the driver as to the resource being marked as available 24 hours. Can someone help me understand the source field in JDE E1 that is being collected and driving this value population?