Hello,
We are struggling to clarify how the Supply grouping can be performed in MPS/MRP.
We have 2 Sales Order, that combined are selling a total of 6 items A010.
There are 2 items linked to Projects/Tasks.
The MPS Demand Workbench for the item is like this:
The issue is that the MPS Supply workbench suggests the release of a single job for that demand:
However we would like to have a line/specific Suggestion for the Demand that is linked to the Projects/Tasks. (e.g. one suggestion to satisfy the demand of 4 items in sales orders; and another suggestion to satisfy the demand of 2 items linked to Projects/Tasks, even though they all have the same Requested Date). Is this possible? Or to have some sort of workaround?