Hello,

We have some Move Order Demands, for items that are built in WIP. When we query the item in the menu Item Supply/Demand it's possible to see their demand:

The above mentioned items are MRP Planned.

However in the MRP Workbench those items are not creating any Supply and/or Demand, which pretty much means that we can't plan them.