Budget Upload in GL Cloud - Significance of Run Name
Back ground
============
Cloud Financials R11. GL Budget upload
Uploaded Budget Data for a single Budget from ADF spreadsheet.
Upload worked OK but we then wanted to amend some of the data - values and accounts.
Test 1 - Same Run name
=====================
It seems that if we use the same run name as the first upload then the new upload will OVERWRITE whatever was uploaded previously for that budget / Run name combination.
Test 2 - Different Run name
=======================
If we use a new run name (same budget) then the new budget data is ADDED to the original budget.
Questions
=====================
1. Is this expected functionality as there does not seem to be anywhere that clearly states expectations. Could someone confirm or provide a link to explain the exact functionality behind the run name?