Hi,

We are in 12.1.3 EBS and using unconstrained Advanced Supply Chain Planning.

I have the following scenario in our business process.

There are few products which are produced at our Factory (in-house) and also from our Co-Manufacturing supplier.

Item Number is same but Recipes are different.

We don't have any fixed % for OSP production, which could be set at sourcing rule. Currently, our internal Production manager decides and suggests OSP production based on his schedule.

Issue is, buyer should know how much ingredients have to be procured for In-house and OSP production as well.

I hope capacity constrained plan would help this out, But our case we are using unconstrained plan option.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center