I need to restore a table to a particular day back in time. The version of the database is 11.2.0.4. The current backup strategy is to perform incremental level 0 backup every first Monday of a month and incremental level 1 on rest of the days in a month.
Is it possible to rolling backward to Jan 26th based on incremental Level 0 of Feb 6th? I got all the backups available from Jan 26th through Feb 6th. Feb 6th is the incremental level 0 and rest of the days between Jan 26th through Feb 6th are incremental level 1 backups.