Hello Gurus,

I have two Unconstrained ASCP plans - ASCP2 is used as demand for ASCP1.

ASCP2 has total 1 parent (forecast) and 3 child items (planned order demand) in its output and I want ASCP1, to use demand of only the child  items from ASCP2 and the demand for the parent item (in ASCP2) should be ignored/should not be fed to ASCP1.

Is there a way to accomplish this ?

In other words, is there a way to not plan for parent item at all, but still plan for the child items underneath. Parent item is not a phantom.  (Unconstrained Plan).