Hi All,

To create new SO our users copied the SO from previous ones. All details including the item cost are copied. But the item cost is old and it is not correct /item cost is different from the current item cost in F4105/

We relieve the inventory on Ship confirm step. The item cost is not updated on ship confirm with the current wеigthed average cost. What we are missing to update the item cost with the correct value from F5104 on ship confirm?

Thanks in advanced!

Regards,