Supply planning by Demand Priority

Hi All

We need to do Supply Planning strictly by demand priority. This includes the transfer as well.

The logic is as follows -

1: Pick up order with priority 1

  • Find on-hand
  • If No on hand then find existing supply
  • If the Item is transferred from the plant then go to plant level ( Here IR-ISO will come in picture)
  • Find On-hand in plant (Org from which item is sourced from)
  • if no on hand in plant then find existing work order
  • if work order exists then explode BOM and repeat cycle for components
  • if no work order then suggest planned order