How to get a report on overhead hours recoded by resources

edited May 2, 2017 12:42PM in Primavera (MOSC) 1 commentAnswered
  1. Would like to create a layout or a report with list of resources with hours recorded on each over head codes per week. Tried both in activity tab and resource tab, but the columns doesnt include overheads. please suggest how to get the overhead data from P6.