Superbackflush Blind execution
Hi,
Below are the setups and results of transaction for the same item in 2 different scenarios
Standard costing with cost elements A1,B1,B3
Scenario 1:
Work order super back flush execution with Hours and Quantities in Interactive mode
R31802A - IC,IH & IM are displayed
R31804 - No variance
Scenario 2:
Work order super back flush execution with Hours and Quantities in Blind mode
R31802A - IC & IM are displayed (NO IH)
R31804 - IV is displayed for IH values
No any changes at any stage other than detailed above.
Have two points here.
1. Is it JDE Standard functionality to have variance i.e. IV instead of IH if Work order super back flush execution with Hours and Quantities in Blind mode.