Can we update Physical % complete from Multiple Level 2 activities to a single activity in Level 1 ?
Hi All,
Please can you help to address my query below,
Can we update Physical % complete from Multiple Level 2 activities to a single activity in Level 1 ?
For instance, we are having the below EPS structure,
#######################################
Level 1 - Programme Level,
=====================
Project A
Level 2 - Sub Programme Level,
==========================
Project 1
Project 2
Below is the Activities Present.
#######################
Project A
Activity A (% Complete Type - Physical)
Project 1
Activity 1 (% Complete Type - Physical)
Activity 2 (% Complete Type - Physical)
Activity 3 (% Complete Type - Physical)
Activity 4 (% Complete Type - Physical)
Activity 5 (% Complete Type - Physical)
Activity 6 (% Complete Type - Physical)
Activity 7 (% Complete Type - Physical)
Activity 8 (% Complete Type - Physical)