Actual Operation Start Date in PS
We are having work orders which have operations that run for about 5 days each. If OP1 starts running on Day1 and the relevant data is collected and a PS plan is run on day3, how would PS know that OP1 had started on Day1 and since the total usage time for the operation resource is 5 days (120 hours), now only 2 days of runtime is left on that resource?
This way, PS will block the operation resource for OP1 only till Day5.
Currently when we run PS plan on Day3, PS schedules OP1 from Day3 to Day7.