We have defined material overhead for a purchased item with absorption basis = Lot.

The objective is to keep the overhead amount constant for each delivery (PO Receipt) regardless of quantity or value of item.

For PO Receipt this works correctly.

But when we do Inter-Org transfer the overhead is absorbed upon receipt based on quantity

Example: If OH rate = $ 100 per Lot and quantity = 10,000 Kgs then the absorbed overhead would be 100 x 10,000 = $ 1,000,000 for the Inter-Org Receipt transaction.

why is this happening?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center