VLT Calculation in Master Item
Hi -
I want to know the standard functionality for calculating Variable lead time in ASCP.
For example if I record the resource usage data like this in x routing:
Process Quantity: 12 Each
Usage: 1
Count: 12
What is happening in my case, the lead time (for 1 Each per 1 Day ) is calculated like this [(1/12)/24 ] .. Regardless to the count.
To find this value 0.003472 in VLT Field in master item .
Is this the standard functionality? And what if I need to include the count into the equation.
Also please advise , what is the best practise with packaging labours , assuming that 1 worker can produce 10 cartons per 1 hour ..if i inserted these as my usage in packaging step , will lead to calculating that i need 1000 hour to produce 10,000 Carton , and considering this our actual lead time is a huge mistake , because of course there are tens of workers working at the same time !!