We are running Production Scheduling 12.1.3, but are in the process of implementing PS v 12.2.6 standalone to schedule and publish the plan generated by 12.1.3. I need to add other attributes to the model but v12.1.3 only supports one attribute where v12.2.6 supports many.

I read through Doc ID 1544941.1 (EBS:PS: Setup Instructions for Defining Attribute-Based Changeovers in PS from EBS), and there was mention of customizations:

* Currently it is not possible to setup or associate multiple attributes to a resource in EBS. Only one attributes can be associated as explained in Note 1544941.1

* Standalone PS allows users to setup multiple attributes to resources and can use User defined ideal sequence setup to sequence/group work orders according to attributes

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center