Hi,
Using Lot control for raw materials.
At manufacturing constants setup is done to hard commit on work order print.
Commitment method is set to 3 – Using Lot Date.
Commitment date method is set to 1 – Lot expiration date.
At item level check availability flag is on.
In processing options of P31113 – Negative quantity on hand is set to 1.
Still when on hand quantity on hand is zero, negative quantity is hard committed against a work order from
secondary location.
Can anyone help me to identify
reason behind this and setup required to avoid this please.
Thanks,