Hi,
In a specific project which the Baseline finish date is later than the Actual project finish date, when copying financial data (Earned Value, Planned Value, and ETC) from Activity Usage Spreadsheet and pasting into Excel, the Planned Value values from the periods beyond the Actual project finish date (when there is no data in ETC) aren't copied.
Is there any way to get around this?
Thanks in advance,