Late supply for components in ASCP plan

edited Sep 26, 2017 5:03AM in Value Chain Planning - EBS (MOSC) 17 commentsAnswered

we have demand in Quarter 1 to Quarter 4.

In Quarter 1 we have on- hand, PO and there is not other supply for the item.  we have more demand in  Q1 compare to (Onhand and PO), and item lead time is 9 weeks. Now related planned orders are showing in the Q2 instead of Q1.

as supply (Onhand and PO) covered aprrox 40 days of demand in Q1, and then in Q1 planned orders are creating.  These planned orders are suppose to start 2nd day of plan run date. Why this delay.

Observed, after coving of onhand/PO quantities only planned orders are created. and this is un-constrained plan.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center