Late supply for components in ASCP plan
we have demand in Quarter 1 to Quarter 4.
In Quarter 1 we have on- hand, PO and there is not other supply for the item. we have more demand in Q1 compare to (Onhand and PO), and item lead time is 9 weeks. Now related planned orders are showing in the Q2 instead of Q1.
as supply (Onhand and PO) covered aprrox 40 days of demand in Q1, and then in Q1 planned orders are creating. These planned orders are suppose to start 2nd day of plan run date. Why this delay.
Observed, after coving of onhand/PO quantities only planned orders are created. and this is un-constrained plan.