Value Chain Planning - EBS (MOSC)

MOSC Banner

Planning does not consider Post Processing Lead Time

edited Jun 23, 2017 12:12AM in Value Chain Planning - EBS (MOSC) 5 commentsAnswered

Hi All,

  We are using ASCP planning in our environment. I could see from the plan output that the post processing lead time is not considered while suggesting planned orders. Both suggested due date and suggested dock date have the same date while we have setup post processing lead time for the item in item attributes screen.

I would expect suggested dock date to be suggested due date - post processing lead time. But in our case it showing the same date for both the values.

We use constrained planning in ECC mode and also we have enforce purchasing lead time constraints enabled.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center