Primavera (MOSC)

MOSC Banner

Earned Value and Schedule % Complete in activities not in Baseline

edited Jun 19, 2017 5:00AM in Primavera (MOSC) 2 commentsAnswered ✓

Hello,

I have a question regarding Earned Value and Schedule % Complete.

(This happened in a real project, but for sake of simplicity I'm showing a test project.)

In an ongoing project, not so rarely it may be possible to have the necessity of "splitting" an activity into two (let's say, an installation of an equipment which was planned in a single activity, but in execution, it would be done in two parts in separate dates for a reason)

(The project before the split of Activity 1)

(Activity 1 split in Activity 1A and 1B - done by copy/paste activity)

When the copied activity Starts and has a non-zero % complete, the Earned Value from this activity isn't calculated, since Activity 1B doesn't exist originally in the baseline (see the picture below).

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center