Pllanned Orders Inside Planning Time Fence
Hi
I am running an EDD Constrained with detailed scheduling plan.
The plan is suggesting planned orders inside the planning time fence.
Past sales orders - 56
On hand qty - 24
PTF - 13
Safety Stock - 70
Planned order suggested for today - 70
Works order next week - 20
works order the following week - 36
This also results in a high projected available balance.