Accrual Write Off GRV/PO linked to a Project
Question:
Project Related PO with project, task, expenditure org, expenditure date information
PO Quantity = 10qty @ R100 unit price = R1000
GRV Quantity = 10qty @ R100 unit price = R1000
Invoice Quantity = 8qty @R100 = R800
Buyer Finally Closed PO
The issue is the Project Management Office (PMO) wants to remaining GRV 2qty which was GRV'd but not Invoiced to be credited back to the project
The only way to clear accruals against a finally closed PO is through an accrual write off.
Question: When buyer write offs remaining 2qty's @ R100 = R200; will the accrual write off credit back against the project in the Project Costing Module?