I was testing a scenario with MRP where we have a WO in WIP (i.e. materials already issued and the first 5 operations completed w/ time & qty recorded) for a part number that already has more than enough in stock to cover the demand.  After MRP run, MRP is suggesting to cancel the WO with Planner Remarks "Cancel FPO".  Is this correct?  Shouldn't MRP defer the WO rather than cancel it since the job had already started?