I want to know what are my options if I want to include fixed costs per work center operations. The
I want to know what are my options if I want to include fixed costs per work center operations.
There 3 fix cost elements I want charged to a work order
1) a fixed lot charge. for example each work order gets a flat $200 lot charge, not based on on hours or quantities produced.
2) a fixed dollar charge ($30) for a particular inspection work center (routing operation), this is a fixed charge and not based on hours or quantities produced. meaning every time a work order gets this work center added to its routing, this fix charge is applied.
3) Create a fix charge per piece inspected. We have a visual inspection work center. When this work center is added to a work order's routing, each unit (Qty) gets a .50 per Qty charge when the operation passes through this work center.