Import/Export Baseline from P6 to P6 with Primavera Gateway
Hi all,
I'm trying to merge 2 differents P6 environements and to syncronize them. I'm trying to use Gateway to do this, but when I try to send Project and Baseline from an environemnt to the other I receive an error message when gateway try to upload the xml extracted : Error: Multiple Projects Found.
I'm asking if anybody has experienced this problem. Looking for a bulletin I've found that with Gateway is it possible to send this kind of data from a P6 to P6. Is it a Bug or there is a specific procedure to send projects and baseline from a P6 database to another P6 database?