Procurement - EBS (MOSC)

MOSC Banner

Supplier schedule past due quantity shown based on Release Need by date or Promise

edited Oct 22, 2017 5:00AM in Procurement - EBS (MOSC) 1 commentAnswered

Hi Friends,

Supplier Schedule workbench past due quantity will be shown on basis of PO Release shipment need by date or Promise date.

for Example: Item: ABC quantity# 31 Need by date: 12-Jun-2017 Promise date: 07-Jul-2017 but past due quantity showing as on 7th Jul 2017 here its considering Promise date.

for item: XYZ quantity :58 need to by date 25-Jun-2017 Promise date: 05-Jul-2017 but past due quantity showing based on need by date.

so bit confused what date basis past due would be shown.

Thanks

Laksh