edited Jul 26, 2017 3:13AM in Value Chain Planning - EBS (MOSC) 6 commentsAnswered ✓

Hi,

I am trying to utilize the Resource Horizontal Plan window in the MRP workbench.

Scenario - Work Order 1234 will be utilizing Resource R-1 for 20 hrs starting 01-Aug and the resource is available only for 8 hrs a day; therefore utilization will be as below.

01-Aug - 8 hrs.

02-Aug - 8 hrs.

03-Aug - 4 hrs.

Based on the above scenario, I expect to see 8 hrs on 01-Aug, 8 hrs on 02-Aug and 4hrs on 03-Aug in the horizontal plan but I see all 20 hrs. on day 1 in the horizontal plan which is causing confusion.

Could you please advise whether I am missing any setup.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center