Can current demand greater than forecast consume forecast from future consumption period?

edited Aug 4, 2017 4:36PM in Manufacturing - JDE1 (MOSC) 4 commentsAnswered ✓

For example:

July Forecast is 10,000

July demand is 20,000

August Forecast is 10,000

MRP is still planning for the August forecast of 10,000.  Is there a setup to force the extra demand in July to consume the August Forecast?

Planning Fence Code 3

Planning Fence Rule H