Multi-Plant MRP calculations not working correctly
Let me lay out the scenario.
- Branch A purchases SKU 123 inventory from Branch B
- Branch B is a distribution center; they source SKU 123 inventory from Branch C
- Branch C is a manufacturing center. On the BOM for SKU 123 is a subassembly 987. The subassembly 987 inventory is normally stored in branch B. So, Branch C sources subassembly 987 from Branch B.
- When Branch B runs out of the subassembly 987 inventory, they source the inventory from another manufacturing facility - Branch D.
I've run MRP and see the following:
- SKU 123 calculates transfer requests from Branch A to Branch B (correct)
- SKU 123 calculates transfer requests from Branch B to Branch C (correct)