Multi-Plant MRP calculations not working correctly

edited Aug 19, 2017 5:03AM in Manufacturing - JDE1 (MOSC) 1 commentAnswered

Let me lay out the scenario.

  • Branch A purchases SKU 123 inventory from Branch B
  • Branch B is a distribution center; they source SKU 123 inventory from Branch C
  • Branch C is a manufacturing center.  On the BOM for SKU 123 is a subassembly 987. The subassembly 987 inventory is normally stored in branch B.  So, Branch C sources subassembly 987 from Branch B.
  • When Branch B runs out of the subassembly 987 inventory, they source the inventory from another manufacturing facility - Branch D.

I've run MRP and see the following:

  • SKU 123 calculates transfer requests from Branch A to Branch B (correct)
  • SKU 123 calculates transfer requests from Branch B to Branch C (correct)

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center