Manufacturing - JDE1 (MOSC)

MOSC Banner

MRP - Freeze Fence

edited Aug 19, 2017 5:03AM in Manufacturing - JDE1 (MOSC) 2 commentsAnswered ✓

Which of the following dates does MRP use to exclude messages for item with Freeze Fence set?  If MRP run date is 08/02/2017 and Freeze Fence is 10 workdays, which of the following dates is used to determine whether the order is inside or outside of the freeze fence?  Based on my test results, it appears that for Expedite/Defer messages, the system uses Recmd'd Complete Date.  For other messages w/o recmd'd dates, the system uses Effective Date?

Start DateRequest DateEffective DateRecmd'd Start DateRecmd'd CompleteRecmd'd Effect. Date

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center