TF Calculations in P6 16.2

edited Aug 23, 2017 4:19PM in Primavera (MOSC) 4 commentsAnswered

WE have two separate projects in P6 version 16.2 operating on the client with inter-project relationships.  The typical EP & CS arrangement.  Total Float is set to Finish-Late Finish and there are a number of Finish on or Before Constraints throughout the projects.  The last activity in the CS project has a constraint date of 3/5/2019 @ 17:00 and a calculated finish of 2/22/19 @ 17:00 and based on the calendar should have a TF of 7 days.  This end milestone and other activities on the critical path are showing 0 TF as if the longest path is selected instead