TF Calculations in P6 16.2
WE have two separate projects in P6 version 16.2 operating on the client with inter-project relationships. The typical EP & CS arrangement. Total Float is set to Finish-Late Finish and there are a number of Finish on or Before Constraints throughout the projects. The last activity in the CS project has a constraint date of 3/5/2019 @ 17:00 and a calculated finish of 2/22/19 @ 17:00 and based on the calendar should have a TF of 7 days. This end milestone and other activities on the critical path are showing 0 TF as if the longest path is selected instead