Hi,

Calculate Manufacturing Lead Times GUI is in Error :

Missing shifts or shift times for resource E525SB in operation 90

RETURNED(failure) bom:bmcalt_calculate_leadtime (upper leadtime)

APP-BOM-20597: Lead time calculation for 1040-00214 failed

I see Resource - E525SB in routing 1040-00214, Viz Department - 525 has Shift assigned and valid(attached)

However the Lead time program still is in Error.

Could you please help see what needs to be setup?

Thanks