Calculate Manufacturing Lead Times GUI
Hi,
Calculate Manufacturing Lead Times GUI is in Error :
Missing shifts or shift times for resource E525SB in operation 90
RETURNED(failure) bom:bmcalt_calculate_leadtime (upper leadtime)
APP-BOM-20597: Lead time calculation for 1040-00214 failed
I see Resource - E525SB in routing 1040-00214, Viz Department - 525 has Shift assigned and valid(attached)
However the Lead time program still is in Error.
Could you please help see what needs to be setup?
Thanks